We are now starting on some of the more advanced features and have been playing around with Maximize and Minimize. I found the minimise not to want to solve and playing around further I cam across the interesting conclusion that Mathcad cannot accommodate multiple accurences of maximize or minimize in the same document.
I duplicated this into a simple sheet duplicating the exact same command next to each other except that the answer is stored into different variables. When moving the one above the other they alternate in solving. This is rather irritating as our model needs to use the data generated to in one case maximize a value and in another case minimize another, but the second one simply does not want to solve.
Has anyone come across the same. Are we doing something wrong or is this a problem in Mathcad.
Please assist
BWB